In short
In South Australia a granny flat is "ancillary accommodation": it sits on the same site as a main house and, to meet the Code's deemed-to-satisfy criteria, has a floor area of no more than 70 m², walls up to 3 m and a roof up to 5 m. It needs Planning Consent and Building Rules Consent through PlanSA, and a footing or slab designed for the site's soil.
Key takeaways
- The Code's deemed-to-satisfy limits are 70 m² of floor area, 3 m wall height and 5 m roof height. Your zone can add its own rules.
- A granny flat needs Development Approval: Planning Consent plus Building Rules Consent, lodged on PlanSA.
- Whether a granny flat may be fully self-contained depends on the current Code wording for your zone. Check before you design the kitchen.
- Much of Adelaide sits on highly reactive clay, so the slab is designed from a site classification, not a standard drawing.
"Granny flat Adelaide" is searched about a thousand times a month in South Australia, mostly by people working out what they can build. The answer comes from the Planning and Design Code, and the build itself rests on engineering that standard plans don't cover: the soil, the slab and how it all sits in your backyard.
Granny flats in SA: quick facts
- Floor area
- Up to 70 m² (deemed-to-satisfy)
- Height
- Walls up to 3 m, roof up to 5 m
- Site
- Same site as the main house, ancillary to it
- Approval
- Planning Consent + Building Rules Consent on PlanSA
- Footings
- Designed from a site classification to AS 2870
- Our quote
- Fixed, in under 20 minutes on average, during business hours
What counts as a granny flat in SA?
In the Planning and Design Code a granny flat is "ancillary accommodation": a small second dwelling that is ancillary to a house on the same site. It isn't a second house in its own right, and it isn't an outbuilding. A shed or studio up to 15 m² can be exempt from approval, but a granny flat people live in is not.
The Code also has a separate pathway for co-located housing (two or more homes sharing gardens), but only where the Co-located Housing Overlay is mapped. For most Adelaide backyards, ancillary accommodation is the relevant category.
How big can a granny flat be in South Australia?
A granny flat can have a floor area of up to 70 m² to meet the Code's deemed-to-satisfy criteria in the Design in Urban Areas module (DTS/DPF 19.4). The same criteria limit wall and roof height.
| Criterion (DTS/DPF 19.4) | Limit | What it means for the design |
|---|---|---|
| Relationship to the house | Ancillary to a dwelling on the same site | One house and one granny flat sharing the block |
| Floor area | Not more than 70 m² | Room for one or two bedrooms, a living area and a bathroom |
| Wall height | Up to 3 m | Single storey in most cases |
| Roof height | Up to 5 m | Pitched roofs are possible within the limit |
| Your zone | Varies | Setbacks, site cover and overlays can add rules |
Planning and Design Code, Version 2026.19. The Code changes every few weeks, so check the online Code for your address before you design.
A design that misses one of these criteria isn't automatically refused. It is assessed on its merits instead, which usually takes longer.
Can a granny flat be self-contained in SA?
It may be, but check the current Code wording for your zone before you plan a full kitchen. This is one point where the published sources don't line up.
An unclear point in the current rules
The Ancillary Accommodation and Student Accommodation Definitions Review Code Amendment (2024) is reported to allow granny flats to be self-contained. The Code text also refers to "shared utilities and shared open space". Which reading applies to your site depends on the current Code and your zone, so confirm it with your council or a planner. It changes the plumbing, the services and sometimes the layout, not the engineering.
What approvals does a granny flat need?
A granny flat needs Development Approval, which in South Australia is Planning Consent plus Building Rules Consent. Both are lodged through the PlanSA portal.
Planning Consent
Checks the use, size, height, setbacks and overlays against the Code. A deemed-to-satisfy application can be lodged with your council or an accredited professional.
Building Rules Consent
Checks the structure against the Building Code (NCC 2022 as amended until 30 April 2027; NCC 2025 from 1 May 2027). It comes from your council or an accredited professional, Building Level 1 to 3. A Level 2 or Level 3 certifier needs the structural calculations certified by an independent technical expert.
Building work
The builder gives the required notices, such as one business day's notice before work starts, and the council may inspect stages like the footings.
Completion
The builder (the licensed building work contractor) signs Part A of the Statement of Compliance and the owner signs Part B, lodged with any certificates or reports the consent lists.
Building indemnity insurance
For domestic building work costing $20,000 or more that needs development approval, the builder must hold building indemnity insurance and give you the certificate before work starts. It is the builder's policy, not cover for engineering advice. See the building approvals guide for the full process.
What engineering does a granny flat need?
A granny flat needs a footing or slab designed for your site's soil, plus structural drawings and calculations for the building consent. The application has to include footing and structural drawings, "calculations or reports" and details of any foundation investigation.
| Item | Why it's needed | Who usually provides it |
|---|---|---|
| Site classification (soil test) | Much of Adelaide sits on highly reactive clay; every site needs its own classification (A, S, M, H1, H2, E or P) | Arranged by the engineer |
| Footing or slab design to AS 2870 | Sets the slab thickness, edge beams and reinforcement for the soil and the building | Structural engineer |
| Frame and bracing | Steel or timber frame, roof tie-down and bracing for wind | Frame supplier or structural engineer |
| Stormwater and site drainage | Keeps roof water and run-off away from new and existing footings | Engineer or designer, connections approved by council |
| Independent certification | Needed when a Building Level 2 or Level 3 certifier grants consent | An independent engineer |

Many granny flats sit on a stiffened raft slab, but a sloping block, deep fill or highly reactive clay can call for deeper edge beams, piers or a different footing system. A slab sized from a standard drawing rather than your soil is a common cause of cracking later. See site classification and footings and granny flat engineering.
What backyard issues change a granny flat design?
Easements, trees, boundaries and drainage change the design more often than the floor plan does. Check them before you settle on where the granny flat goes.
- SA Water easements. No building over water easements. A dwelling over a sewer easement (but not over the main) must keep its footing zone of influence clear of the trench and stay 1.5 m from the main's centre, with a maximum length of 6.5 m. Apply to SA Water at the same time as council, and confirm the current fact sheet with them.
- Trees. Your site plan must show any regulated tree on your land or the neighbour's. Trees within 3 m of a house are generally exempt, except eucalypts, Corymbia, Angophora and willow myrtle. See trees and house cracks.
- Boundaries. Excavating close to a neighbour's land, or filling within 600 mm of the boundary, can require a section 139 notice. See neighbour excavation.
- Slopes and retaining walls. A cut-and-fill pad may need a retaining wall, and a wall retaining more than 1 m needs approval. See retaining walls.
- Stormwater. A new roof adds run-off to a yard that may already drain poorly. See stormwater rules in Adelaide.
We engineer granny flats across Greater Adelaide, from growth areas such as Mount Barker and Morphett Vale to the older northern suburbs around Salisbury.
When should you call a structural engineer for a granny flat?
Call an engineer once you have a site plan and a floor plan, and before you sign a build contract that includes a standard slab. That's the point where the soil, the easements and the slope can still change the price.
- You need the footing or slab design and calculations for Building Rules Consent
- The block slopes, has fill, or needs a retaining wall
- A sewer easement, a large tree or a neighbour's footing is close to where it will sit
- Your certifier needs independent certification of the structural calculations
- A kit or modular supplier needs footings designed for your site
We are engineering only. We don't sell or build granny flats, so the design is about your site. Get a fixed quote or call 08 7083 9853.
Need an engineer?
Planning a granny flat?
Send the site plan, floor plan and any soil report. You get a fixed quote for the engineering in under 20 minutes on average, during business hours.
Sources
- PlanSA, Planning and Design Code, Version 2026.19 (8 October 2026). Design in Urban Areas, DTS/DPF 19.4 (ancillary accommodation). The Code changes often: check the online Code for your zone
- Planning, Development and Infrastructure (General) Regulations 2017. Reg 25 (building consent and independent technical experts), reg 57(8)(c), reg 104 (Statement of Compliance), Schedule 8 cl 2(1) (what an application includes)
- Department for Infrastructure and Transport, Engaging an accredited professional as a decision-maker
- SAFA, Building indemnity insurance. Domestic building work of $20,000 or more that needs development approval
- SA Water, Encroachment over easement (fact sheet)
- PlanSA, Significant and regulated trees