Stormwater

Stormwater rules in Adelaide: tanks, detention and the kerb

Rainwater tank sizes from the Stormwater Management Overlay, detention and slow-release orifices, kerb connections, SA Water easements, and why the old 1 kL rule no longer applies.

Slimline rainwater tank beside a new house, with a PVC stormwater pipe in an open trench running to a concrete pit with a grate and a laser level on a tripod

In short

Where the Planning and Design Code's Stormwater Management Overlay applies, a new home's rainwater tank is sized by site area: 1,000 L, 2,000 L or 4,000 L of retention, plus 1,000 L of detention on small or mostly hard-surfaced sites, released through a 20–25 mm orifice. The old building-rule 1 kL tank no longer applies, and kerb connections need council approval.

Key takeaways

  • Retention: 1,000 L under 200 m², 2,000 L for 200–400 m², 4,000 L from 401 m². Detention of 1,000 L is added on small or low-perviousness sites.
  • SA Part H9, the old building-rule 1 kL tank, does not apply in South Australia any more. The Code overlay sets tank sizes now.
  • Connecting to the kerb needs council approval. Councils set pipe sizes, outlet spacing and distances from street trees.
  • On reactive clay, water in the wrong place moves footings. Drainage is part of the structure, not an afterthought.

Close to half of Australia's searches for "drainage plan" come from South Australia, and for good reason. Councils ask for one with many building applications, the tank rules changed recently, and on Adelaide's reactive clay, water in the wrong place cracks houses.

Stormwater rules: quick facts

Retention tank
1,000 / 2,000 / 4,000 L by site area
Detention
1,000 L on small or low-perviousness sites
Orifice
20–25 mm slow release
Old 1 kL rule
SA Part H9 no longer applies
Kerb connection
Council approval needed
Our drainage plans
From $790 + GST ($869 inc GST)

How big does a rainwater tank need to be in Adelaide?

The tank size depends on your site area: 1,000 L of retention under 200 m², 2,000 L for 200–400 m², and 4,000 L for 401 m² or more. These are the deemed-to-satisfy volumes in the Code's Stormwater Management Overlay (DTS/DPF 1.1, Table 1).

Rainwater retention required by site area

  • Under 200 m²+ 1,000 L detention1,000 L
  • 200–400 m²+ 1,000 L detention if under 30% pervious2,000 L
  • 401 m² or more+ 1,000 L detention if under 35% pervious4,000 L
Figure 1Retention is water you keep and use. Detention (1,000 L) is added on every site under 200 m², on 200–400 m² sites with less than 30% perviousness, and on larger sites with less than 35%.Source: Planning and Design Code v2026.19, Stormwater Management Overlay, Table 1

The overlay applies to detached, semi-detached and row dwellings, groups of fewer than 5 dwellings, co-located housing and flat dwellings. To meet it, the tank also has to:

  • Collect from at least 60% of the roof for a detached (not battle-axe), semi-detached or row dwelling, and 80% for other types
  • Be plumbed to a toilet or the laundry cold water outlets on sites under 200 m², or to one toilet and the laundry cold outlets on 200 m² and over
  • Have a 20–25 mm slow-release orifice wherever detention is required

The dwelling's roof must also make up at least 80% of the site's hard (impervious) area. The overlay isn't mapped everywhere, so check your address in the SA Property and Planning Atlas (SAPPA) or on PlanSA.

What is stormwater detention, and how is it different from retention?

Detention holds water back for a short time and releases it slowly; retention keeps it for use. A detention tank, or the top part of a combined tank, fills during a storm and drains out through the small orifice over the following hours.

 RetentionDetention
PurposeReuse in toilets and laundrySlow the peak flow to the street
Volume1,000–4,000 L by site area1,000 L where required
OutletPump and plumbing to fixtures20–25 mm orifice to the stormwater system
When it's emptyRarely: you use it downSoon after each storm

Perviousness is the share of your site that soaks up rain, such as lawn and garden beds. Large houses, driveways and paved yards on small blocks push it down, which is why detention is required more often on infill sites. MBS 009 "On-site retention of stormwater" sets out cost-effective solutions, and Green Adelaide is preparing guidance on meeting the Code's stormwater requirements.

Does the 1,000 L rainwater tank rule still apply in SA?

No. The old building-rule requirement for a plumbed 1 kL tank came from SA Part H9, a South Australian variation to the National Construction Code. MBS 007 Amendment 5 (December 2025) and Amendment 6 (April 2026) both state that "SA Part H9 does not apply in South Australia".

Why you still see the old rule

Even under NCC 2022, SA H9 only applied to HomeBuilder grant development. The sa.gov.au rainwater tank page, last updated in December 2023, still describes the old 1 kL rule. For a house today, the Stormwater Management Overlay sets the tank size, and your consent conditions are what count.

Can I connect stormwater to the kerb in Adelaide?

Yes, with council approval. Each council sets its own conditions. In Holdfast Bay, for example, the owner is responsible for the pipe through the verge and the outlet in the kerb.

Council exampleWhat it requires
Holdfast BaySection 221 (Local Government Act) application, $80 fee. Pipes 75–100 mm, one outlet per 10 m of frontage (up to 2 × 100 mm side by side), at least 2 m from street trees and 0.2 m from inverts
Unley (policy reported December 2025)All stormwater to the kerb water table, none onto footpaths, up to 20 L/s per connection, outlets at least 20 m apart, no groundwater to the kerb
Lots below road levelGravity to the kerb may not work: grated drains, a pump or on-site detention are needed

Holdfast Bay from its connection form page. Unley from a secondary summary of its December 2025 policy; confirm current conditions with your council.

What are the rules for building near an SA Water easement?

You can't build over an SA Water water easement or a sewer access point, and anything over a sewer easement has clearance rules. Applications go to SA Water at the same time as council.

  • A house over an easement but not over a main: footing zone of influence clear of the trench, 1.5 m to the main's centre, concrete in 1.0 m slabs within 0.6 m of the main's centreline, and a maximum length of 6.5 m.
  • Sheds and carports: 1.0 m clearance if demountable, 1.5 m if masonry. Over a main they must be demountable, with 2.4 m openings for access.
  • Pools and tanks in an easement must keep the footing zone of influence clear of the sewer trench.

SA Water's encroachment fact sheet is undated, so confirm the current requirements with SA Water before you finalise a design.

Why does stormwater matter for footings on reactive clay?

Because water changes the volume of reactive clay. Much of Adelaide sits on highly reactive clay; every site needs its own classification. Clay that gets wet swells and lifts footings (heave), and clay that dries shrinks and lets them drop.

The 2016 Modbury North soil study found the clays there react to ponding and leaking service pipes, with significant surface heave in wet months. The same thing happens around the city when downpipes discharge at the wall, overflows dump next to the footings, or paths fall towards the house.

Do

  • Pipe every downpipe and tank overflow to the street system or an approved outlet
  • Grade paving and garden beds to fall away from the walls
  • Fix leaking stormwater and sewer pipes quickly

Don't

  • Let a downpipe or overflow discharge against the footing
  • Install air drains in reactive clay without geotechnical engineering advice
  • Assume the old drainage still works after an extension or new paving

What does a stormwater or drainage plan show?

A drainage plan shows where every litre of roof and surface water goes, at what size and fall, and how it leaves the site. Councils and certifiers ask for one with many building applications, and it is what your plumber builds from.

  • Roof catchments, downpipes and the share of roof connected to the tank
  • Tank sizes for retention and detention, with the orifice and overflow
  • Pipe sizes, falls and pits, with levels from the house to the outlet
  • The kerb outlet location, or a pump or detention solution for low lots
  • Easements, existing services and clearances to footings and street trees

Our stormwater and drainage plans start from $790 + GST ($869 inc GST). Many go with new footings or a granny flat: see site classification and footings and granny flat engineering.

When should you call a structural engineer about stormwater?

  • Council or your certifier has asked for a stormwater management or drainage plan
  • You're building on a small or infill site where detention is likely to be required
  • The block sits below the road, so water can't fall to the kerb
  • Cracks appeared after wet weather or near a leaking pipe. See cracks in walls
  • You want to build near an SA Water easement and need the footing clearances designed

What to send

A site plan, the roof plan and any council request. Get a fixed quote in under 20 minutes on average, during business hours, or call 08 7083 9853.

Sources

  1. PlanSA, Planning and Design Code, Version 2026.19 (8 October 2026). Stormwater Management Overlay, DTS/DPF 1.1 and Table 1. Check the online Code for the current version
  2. PlanSA, MBS 007 Modifications to the Building Code of Australia for NCC 2022 (Amendment 6, April 2026). "SA Part H9 does not apply in South Australia"
  3. Australian Building Codes Board, NCC 2022 Volume Two, SA Part H9 Water efficiency
  4. PlanSA, Ministerial Building Standards. MBS 009 On-site retention of stormwater
  5. City of Holdfast Bay, Stormwater pipe connection form
  6. SA Water, Encroachment over easement (fact sheet)
  7. Geological Survey of South Australia (SARIG), Modbury North soil study, Sheard and others (2016)

FAQ

Stormwater in Adelaide: FAQs

Still unsure? Call 08 7083 9853 or send photos for a fixed quote.

What size rainwater tank do I need for a new house in Adelaide?

Where the Stormwater Management Overlay applies, the deemed-to-satisfy retention volume is 1,000 L on sites under 200 m², 2,000 L on 200–400 m² and 4,000 L on 401 m² or more. Small or mostly hard-surfaced sites also need 1,000 L of detention.

Is a 1,000 L rainwater tank still compulsory in SA?

Not as a building rule. MBS 007 now says SA Part H9, the provision behind the old 1 kL tank, does not apply in South Australia, and tank sizes for houses come from the Code's Stormwater Management Overlay instead. Some older government pages still describe the old rule.

What is a stormwater detention tank?

A detention tank holds stormwater for a short time and lets it out slowly through a small orifice (20–25 mm under the overlay), so the street drains don't get a sudden rush. Retention, by contrast, is water you keep and use.

Do I need council approval to connect stormwater to the kerb?

Yes. Councils approve kerb connections and set their own conditions. In Holdfast Bay, for example, the application is a section 221 form with an $80 fee, and the owner is responsible for the pipe through the verge and the kerb outlet.

Can I build over an SA Water easement?

Not over a water easement or a sewer access point. A house over a sewer easement but not over the main must keep its footings clear of the trench and stay 1.5 m from the main's centre; apply to SA Water at the same time as council.

Who regulates the plumbing from my rainwater tank?

The Office of the Technical Regulator regulates the plumbing from the tank into the house. The stormwater connections, such as roof to tank and the tank overflow, are regulated by council under the PDI Act.