In short
In Salisbury, a retaining wall with a fence on top needs development approval once the two together exceed 2.1 m, measured from the lower ground. The City of Salisbury then asks for the engineer's design, including calculations for the footings and connection details. We design these walls from $790 + GST ($869 inc GST), and engineer pools, granny flats and verandahs across Salisbury, Mawson Lakes and Paralowie.
Structural engineer Salisbury: local facts
- Council
- City of Salisbury
- Wall plus fence
- Approval once the combined height exceeds 2.1 m, measured from the lowest side of the ground
- What council asks for
- A site plan, elevations, construction details and the engineer's footing calculations and connection details
- Pool applications
- Plans show the setbacks from the boundaries, the safety features and where the pump goes; council inspects once the pool is in
- Corner blocks
- A fence over 1 m within 6 m of a road intersection needs approval, unless a 4 m × 4 m corner cut-off is provided
Wall plus fence over 2.1 m: what does Salisbury require?
Development approval, once the retaining wall and the fence on it add up to more than 2.1 m, measured from the lowest side of the ground. A fence alone is exempt up to 2.1 m, and a wall alone is exempt while it retains no more than 1 m. The City of Salisbury's own page says an application is needed once a wall is 1 m or greater, so treat a wall right on 1 m as needing one.
The combined rule catches ordinary jobs. A 1.8 m Colorbond fence is exempt on level ground, but put it on a 600 mm wall and the total from the low side is 2.4 m.
| Retaining wall | Fence on top | Height from the low side | Approval on height? |
|---|---|---|---|
| 300 mm | 1.8 m | 2.1 m | No, it doesn't exceed 2.1 m |
| 600 mm | 1.8 m | 2.4 m | Yes, with the engineer's footing calculations |
| 900 mm | 1.5 m | 2.4 m | Yes |
| 1.2 m | None | 1.2 m | Yes: the wall retains more than 1 m |
Illustrative examples. Other triggers apply too: masonry fences over 1 m, fences over 1 m within 6 m of a road intersection, pool safety fences and land in a flood overlay. Source: the City of Salisbury fencing page and PDI Regulations Schedule 4.
Council wants the engineer's design because the fence changes how the wall behaves. Wind on a solid fence pushes on its posts, and when those posts sit in or just behind the wall, the wall and its footing have to resist that push as well as the soil. Our design gives the post footings, the wall section and the connection between them, ready to lodge with the site plan and elevations through PlanSA. Retaining wall design starts at $790 + GST ($869 inc GST).
Who pays for a retaining wall between Salisbury neighbours?
The owner who altered the natural lie of the land is responsible for the wall, and if both neighbours cut or filled, they are jointly responsible. Council's guidance treats the cost split as a civil matter between neighbours and says it has no authority in boundary disputes.
Where the wall sits follows the same logic. If only one owner needs a wall on the boundary, it goes wholly on that owner's side with only its outside face on the line. If both share it equally, it can straddle the boundary. A design that shows how much ground each side retains makes that conversation easier. The retaining wall rules guide covers the state-wide picture, including how tiered walls are measured.
What does a pool approval in Salisbury involve?
Planning and building approval for any pool deeper than 300 mm or fitted with a filter, including inflatable ones, with plans showing the setbacks from your boundaries, the pool's size and safety features, and the location of the pump and other equipment. The state's pool guidance says council checks the barrier, pump safety and the adequacy of the structural support.
That last point is the engineer's part. A shell near a boundary, a fence footing or the house needs a design that suits the soil and the loads around it, and a dig close to the boundary may require a section 139 notice to your neighbour. The safety barrier must be finished within two months of the pool being completed or before it is filled, whichever comes first, and you notify council for an inspection once everything is in. Pool engineering starts at $890 + GST ($979 inc GST).
Selling a home with a pool approved or built before 1 July 1993? Its barrier must meet Ministerial Building Standard MBS 004 by settlement, as the City of Salisbury's pool page explains. That's a barrier upgrade rather than a structural one, but a cracked shell or a leaning wall beside it is worth a structural inspection.
Granny flat or verandah in Salisbury: is an engineer needed?
Usually, yes. A granny flat needs a site classification and a footing or slab design, and a roofed verandah or carport usually needs member sizes and footing details for its approval.
Under the Code's urban design standard, ancillary accommodation of up to 70 m², with walls up to 3 m and a roof up to 5 m high, meets the deemed-to-satisfy criteria, but your zone decides what's allowed, so check it first (the granny flat rules guide explains). Much of Adelaide sits on highly reactive clay and every site needs its own classification, so the soil test is arranged as part of granny flat engineering, priced as a fixed quote.
An open pergola is exempt if it has no solid roof, open sides, is no higher than 4 m and doesn't sit in front of the building line. Add a solid roof and that exemption no longer applies. Verandah, carport and deck engineering starts at $490 + GST ($539 inc GST), and an engineer's certificate for a structure that's already built starts at $390 + GST ($429 inc GST).