In short
In South Australia you apply through PlanSA. Building work that is development usually needs Planning Consent (against the Planning and Design Code) and Building Rules Consent (against the Building Code), which together give Development Approval. Some work isn't development, such as a retaining wall up to 1 m, a fence up to 2.1 m or a low deck, but each exemption has conditions.
Key takeaways
- Everything is lodged on PlanSA. Planning Consent plus Building Rules Consent gives Development Approval.
- Building Rules Consent comes from the council or an accredited professional (a building certifier at Level 1, 2 or 3).
- Not development: retaining walls up to 1 m, fences up to 2.1 m, decks up to 500 mm high and 900 mm from a boundary, open pergolas up to 4 m, sheds up to 15 m². Each has conditions.
- Removing a load-bearing wall needs approval. Underpinning usually needs building consent; we confirm with your council or certifier.
- NCC 2022 (as amended) applies in SA until 30 April 2027, and NCC 2025 from 1 May 2027.
South Australia's approval system now runs under the Planning, Development and Infrastructure Act 2016 and the PlanSA portal, and older leaflets still carry earlier terms and figures. This guide explains the current system in plain terms: the two main consents, who grants them, what you lodge on PlanSA, which small jobs need no approval and the conditions attached to each exemption.
Building approvals in SA: quick facts
- Where you apply
- The PlanSA portal, for every council
- Planning Consent
- Assessed against the Planning and Design Code
- Building Rules Consent
- Assessed against the Building Code (NCC 2022 as amended)
- Development Approval
- Granted once every required consent is in place
- Exempt walls
- Retaining walls up to 1 m, with exceptions
- Next NCC
- NCC 2025 Building Code from 1 May 2027
What is the difference between Planning Consent and Building Rules Consent?
Planning Consent asks whether the development suits the site under the Planning and Design Code; Building Rules Consent asks whether it will be built safely under the Building Code. A granny flat can pass the planning test on size and siting and still need a footing design before the building test is met.
| Consent | Checks against | Typical questions | Who assesses |
|---|---|---|---|
| Planning Consent | Planning and Design Code: zones, overlays, policies | Use, size, height, setbacks, heritage and character, trees, stormwater | Council, or an accredited professional for Deemed-to-Satisfy applications |
| Building Rules Consent | Building Code (the NCC as varied for SA) and Ministerial Building Standards | Structure, footings, wind and site class, fire safety, energy, pool barriers | Council, or an accredited professional at Building Level 1–3 |
| Development Approval | All required consents | Are they all granted? | Issued once every consent is in place |
The Code is updated every fortnight. Check the zone and overlays for your site in the online Planning and Design Code before you rely on a number.
Who grants Building Rules Consent in South Australia?
The council or an accredited professional building certifier grants Building Rules Consent, and you choose which. Certifiers at Building Levels 1, 2 and 3 can grant consent within the limits of their level; a Level 4 inspector can't. A Level 2 or Level 3 certifier also needs the structural calculations certified by an independent technical expert (reg 25(5) and (7)). For Deemed-to-Satisfy applications you can also choose council or an accredited professional as the planning decision-maker.
The levels, and who does what, are set out in do I need a structural engineer, a building inspector or a certifier?
How does the building approval process work in SA?
You check what applies to your site, prepare the drawings and engineering, lodge on PlanSA, receive each consent, then build with the notices the regulations require.
- Before you design
Check the zone and overlays
The Code sets the zone and any overlays (heritage, bushfire, flooding, coastal, trees, stormwater) that change what is exempt and what you must show.
- Design
Drawings, site classification and engineering
Plans and, where the work needs them, a site classification, a footing design to AS 2870 and structural drawings and calculations.
- Lodge
Apply on PlanSA
One application, assessed by council or the accredited professionals you choose.
- Assessment
Planning Consent, then Building Rules Consent
Each consent can carry conditions, including the certificates or reports to supply at completion (reg 57(8)(c)).
- Approval
Development Approval
Issued once every required consent is granted. Building work can start only after this.
- Build and finish
Notices, inspections and the Statement of Compliance
The builder notifies council before starting and at the stages the consent lists, then lodges the Statement of Compliance.
What building work is exempt from approval in SA?
Schedule 4 of the General Regulations lists work that is not development, so it needs no approval, as long as every condition is met. None of these exclusions apply to a State heritage place (reg 3C), and overlays remove several of them.
| Work | Not development when | Needs approval when |
|---|---|---|
| Retaining wall | It retains a difference in ground levels of 1 m or less (tiered walls are measured on the overall difference) | Over 1 m; or in a flood zone, subzone or overlay, within 100 m of the coast, or on a local or State heritage place |
| Fence | Up to 2.1 m, measured from the lower of the two finished ground levels | Masonry over 1 m; over 1 m within 6 m of a corner; pool safety fences; Historic Area front fences; brush fences within 3 m of a house; flood overlays, the Hills Face Zone, the Significant Landscape Protection Overlay |
| Retaining wall with a fence on top | Wall plus fence is 2.1 m or less, measured from the low side | Over 2.1 m combined; councils ask for the engineer's footing calculations |
| Deck | No point higher than 500 mm above natural ground, and no part within 900 mm of a boundary | Bushfire prone areas, the Historic Area Overlay, the Coastal Areas Overlay, the Hills Face Zone, the Significant Landscape Protection Overlay |
| Pergola | No solid roof, open sides, no higher than 4 m and not in front of the building line | A local heritage place; a solid roof, enclosed sides, over 4 m, or in front of the building line |
| Outbuilding (shed) | Up to 15 m², roof span up to 3 m and up to 2.5 m high | Larger, or where other conditions aren't met |
| Water tank | Above ground, up to 10 m² and 40,000 L, up to 4 m high (15 m² and 60,000 L in bushfire overlays) | Outside these limits |
| Swimming pool | Not deeper than 300 mm (and, for an above-ground or inflatable pool, no filtration system) | Deeper than 300 mm; an above-ground or inflatable pool with filtration; any pool in the Hills Face Zone |
| Repairs and internal alterations | No demolition beyond fixtures, fittings or non-load-bearing partitions, and no adverse effect on structural soundness | Removing or altering a load-bearing wall, or any work that affects the structure |
PDI (General) Regulations 2017, Schedule 4 clause 4, version of 29.10.2026; wall-plus-fence rule from the Law Handbook and council guidance. Confirm with your council or certifier for your site.
Exempt doesn't mean no engineering
A 900 mm wall holding up a driveway, or a 2 m fence on a slope, can be exempt and still need a proper design. Exemption only means no approval: the wall still has to stand up.
Which common jobs need approval in SA?
Most structural work on a house needs approval, along with anything that falls outside the conditions above.
- Removing a load-bearing wall: outside the internal alterations exemption. See wall removal and beam design.
- Underpinning: usually needs building consent; we confirm with your council or certifier. See underpinning assessment.
- Extensions, second storeys and new homes: Planning Consent and Building Rules Consent. See extensions and renovations.
- Granny flats: the Code's Deemed-to-Satisfy criteria for ancillary accommodation are a floor area up to 70 m², walls up to 3 m and a roof up to 5 m high; check the zone. Read granny flat rules in SA.
- Pools deeper than 300 mm and their safety barriers. See pool engineering.
- Retaining walls over 1 m, and wall-plus-fence combinations over 2.1 m. See retaining wall engineering.
- Demolition of a local heritage place or a building in the Historic Area Overlay. Character Areas follow different rules, so check with council. Read looking after a bluestone home.
- Excavation or fill over 9 m³ on coastal land (Schedule 3 clause 5).
What does a building consent application need?
Schedule 8 of the General Regulations lists what a Building Rules Consent application must include, and most of it comes from the designer and the engineer.
- A site plan at 1:500, showing easements, trees that affect or are affected by the work, and "the location of any regulated tree on the site or on adjoining land"
- Footing and structural drawings at 1:200, and specifications
- "Calculations or reports", such as the engineer's structural calculations
- "Details in writing of any foundation investigations": the site classification. See site classification and footings
- Retaining walls: location, minimum and maximum heights, elevations at 1:200 and materials
- Pools: a 1:200 plan with the pool's dimensions, safety features, setbacks from boundaries and pump location
What happens during and after the build?
The builder gives the council notice at set points, the council inspects, and the work finishes with a Statement of Compliance.
| Step | The rule |
|---|---|
| Notices (reg 93) | 1 business day before work starts; before any stage the council specifies (1 business day in Metropolitan Adelaide, 2 outside it); any stage in the consent; 1 business day before completion. Penalty up to $10,000, expiation fee $750 |
| Council inspections | Current policies inspect 66% of new houses, 90% of new commercial buildings and 100% of new swimming pools |
| Statement of Compliance (reg 104) | Part A signed by the licensed building work contractor (or, where there is none, a registered building work supervisor or a building certifier), Part B by the owner; lodged with any certificates or reports the consent lists. Not needed for Class 10 buildings other than pools and bushfire shelters |
| Occupancy (reg 103) | A Class 10 building needs no certificate of occupancy. A house can't be lived in before completion unless it is structurally sound, weatherproof, has its facilities and smoke alarms, and meets the bushfire rules |
| Building indemnity insurance | The builder needs it for domestic work costing $20,000 or more that needs approval, with $250,000 cover, and must give you the certificate before work starts. It is a builder's policy, not cover for engineering advice |
PDI (General) Regulations 2017, PlanSA and SAFA. Owner-builders give the notices themselves.
When to call a structural engineer
Call an engineer as soon as you know the work touches the structure or the ground, so the drawings go in once and complete.
- Your designer or certifier needs footing design, structural drawings or calculations
- A Level 2 or Level 3 certifier needs the structural calculations independently certified. See engineer's certificates, from $390 + GST
- A wall, deck or fence sits just over an exemption limit, or near a boundary
- You plan to remove a wall and don't know whether it is load-bearing
- The consent lists a certificate or report to lodge at completion
One fixed quote for the engineering
Send your plans or photos. We reply with a fixed quote in under 20 minutes on average, during business hours, and we say so if the job needs no engineer. Get a fixed quote.
Need an engineer?
Need drawings for your application?
Send your plans or photos. You'll have a fixed quote for the engineering in under 20 minutes on average, during business hours.
Sources
- Planning, Development and Infrastructure (General) Regulations 2017 (SA), version of 29.10.2026. Schedule 4 clause 4 (work that is not development), reg 3C, reg 25, reg 57(8)(c), reg 93, reg 103, reg 104 and Schedule 8 clause 2(1)
- Planning and Design Code, Version 2026.19 (8 October 2026). The Code changes every fortnight; check the online Code for your site
- Department for Infrastructure and Transport, Fact sheet: Engaging an accredited professional as a decision-maker
- PlanSA, Inspections and compliance
- PlanSA, NCC 2025 state updates
- Legal Services Commission of SA, Law Handbook: retaining walls and fences
- SAFA, About building indemnity insurance
- sa.gov.au, Pool and spa safety