Building approvals in SA: consents and what's exempt

Planning Consent, Building Rules Consent and Development Approval on PlanSA: who grants them, what the application needs, and which jobs are exempt, with the conditions that catch people out.

New timber-framed second storey with roof trusses and scaffolding on a single-storey red-brick house

In short

In South Australia you apply through PlanSA. Building work that is development usually needs Planning Consent (against the Planning and Design Code) and Building Rules Consent (against the Building Code), which together give Development Approval. Some work isn't development, such as a retaining wall up to 1 m, a fence up to 2.1 m or a low deck, but each exemption has conditions.

Key takeaways

  • Everything is lodged on PlanSA. Planning Consent plus Building Rules Consent gives Development Approval.
  • Building Rules Consent comes from the council or an accredited professional (a building certifier at Level 1, 2 or 3).
  • Not development: retaining walls up to 1 m, fences up to 2.1 m, decks up to 500 mm high and 900 mm from a boundary, open pergolas up to 4 m, sheds up to 15 m². Each has conditions.
  • Removing a load-bearing wall needs approval. Underpinning usually needs building consent; we confirm with your council or certifier.
  • NCC 2022 (as amended) applies in SA until 30 April 2027, and NCC 2025 from 1 May 2027.

South Australia's approval system now runs under the Planning, Development and Infrastructure Act 2016 and the PlanSA portal, and older leaflets still carry earlier terms and figures. This guide explains the current system in plain terms: the two main consents, who grants them, what you lodge on PlanSA, which small jobs need no approval and the conditions attached to each exemption.

Building approvals in SA: quick facts

Where you apply
The PlanSA portal, for every council
Planning Consent
Assessed against the Planning and Design Code
Building Rules Consent
Assessed against the Building Code (NCC 2022 as amended)
Development Approval
Granted once every required consent is in place
Exempt walls
Retaining walls up to 1 m, with exceptions
Next NCC
NCC 2025 Building Code from 1 May 2027

What is the difference between Planning Consent and Building Rules Consent?

Planning Consent asks whether the development suits the site under the Planning and Design Code; Building Rules Consent asks whether it will be built safely under the Building Code. A granny flat can pass the planning test on size and siting and still need a footing design before the building test is met.

ConsentChecks againstTypical questionsWho assesses
Planning ConsentPlanning and Design Code: zones, overlays, policiesUse, size, height, setbacks, heritage and character, trees, stormwaterCouncil, or an accredited professional for Deemed-to-Satisfy applications
Building Rules ConsentBuilding Code (the NCC as varied for SA) and Ministerial Building StandardsStructure, footings, wind and site class, fire safety, energy, pool barriersCouncil, or an accredited professional at Building Level 1–3
Development ApprovalAll required consentsAre they all granted?Issued once every consent is in place

The Code is updated every fortnight. Check the zone and overlays for your site in the online Planning and Design Code before you rely on a number.

Who grants Building Rules Consent in South Australia?

The council or an accredited professional building certifier grants Building Rules Consent, and you choose which. Certifiers at Building Levels 1, 2 and 3 can grant consent within the limits of their level; a Level 4 inspector can't. A Level 2 or Level 3 certifier also needs the structural calculations certified by an independent technical expert (reg 25(5) and (7)). For Deemed-to-Satisfy applications you can also choose council or an accredited professional as the planning decision-maker.

The levels, and who does what, are set out in do I need a structural engineer, a building inspector or a certifier?

How does the building approval process work in SA?

You check what applies to your site, prepare the drawings and engineering, lodge on PlanSA, receive each consent, then build with the notices the regulations require.

  1. Before you design

    Check the zone and overlays

    The Code sets the zone and any overlays (heritage, bushfire, flooding, coastal, trees, stormwater) that change what is exempt and what you must show.

  2. Design

    Drawings, site classification and engineering

    Plans and, where the work needs them, a site classification, a footing design to AS 2870 and structural drawings and calculations.

  3. Lodge

    Apply on PlanSA

    One application, assessed by council or the accredited professionals you choose.

  4. Assessment

    Planning Consent, then Building Rules Consent

    Each consent can carry conditions, including the certificates or reports to supply at completion (reg 57(8)(c)).

  5. Approval

    Development Approval

    Issued once every required consent is granted. Building work can start only after this.

  6. Build and finish

    Notices, inspections and the Statement of Compliance

    The builder notifies council before starting and at the stages the consent lists, then lodges the Statement of Compliance.

What building work is exempt from approval in SA?

Schedule 4 of the General Regulations lists work that is not development, so it needs no approval, as long as every condition is met. None of these exclusions apply to a State heritage place (reg 3C), and overlays remove several of them.

WorkNot development whenNeeds approval when
Retaining wallIt retains a difference in ground levels of 1 m or less (tiered walls are measured on the overall difference)Over 1 m; or in a flood zone, subzone or overlay, within 100 m of the coast, or on a local or State heritage place
FenceUp to 2.1 m, measured from the lower of the two finished ground levelsMasonry over 1 m; over 1 m within 6 m of a corner; pool safety fences; Historic Area front fences; brush fences within 3 m of a house; flood overlays, the Hills Face Zone, the Significant Landscape Protection Overlay
Retaining wall with a fence on topWall plus fence is 2.1 m or less, measured from the low sideOver 2.1 m combined; councils ask for the engineer's footing calculations
DeckNo point higher than 500 mm above natural ground, and no part within 900 mm of a boundaryBushfire prone areas, the Historic Area Overlay, the Coastal Areas Overlay, the Hills Face Zone, the Significant Landscape Protection Overlay
PergolaNo solid roof, open sides, no higher than 4 m and not in front of the building lineA local heritage place; a solid roof, enclosed sides, over 4 m, or in front of the building line
Outbuilding (shed)Up to 15 m², roof span up to 3 m and up to 2.5 m highLarger, or where other conditions aren't met
Water tankAbove ground, up to 10 m² and 40,000 L, up to 4 m high (15 m² and 60,000 L in bushfire overlays)Outside these limits
Swimming poolNot deeper than 300 mm (and, for an above-ground or inflatable pool, no filtration system)Deeper than 300 mm; an above-ground or inflatable pool with filtration; any pool in the Hills Face Zone
Repairs and internal alterationsNo demolition beyond fixtures, fittings or non-load-bearing partitions, and no adverse effect on structural soundnessRemoving or altering a load-bearing wall, or any work that affects the structure

PDI (General) Regulations 2017, Schedule 4 clause 4, version of 29.10.2026; wall-plus-fence rule from the Law Handbook and council guidance. Confirm with your council or certifier for your site.

Exempt doesn't mean no engineering

A 900 mm wall holding up a driveway, or a 2 m fence on a slope, can be exempt and still need a proper design. Exemption only means no approval: the wall still has to stand up.

Which common jobs need approval in SA?

Most structural work on a house needs approval, along with anything that falls outside the conditions above.

  • Removing a load-bearing wall: outside the internal alterations exemption. See wall removal and beam design.
  • Underpinning: usually needs building consent; we confirm with your council or certifier. See underpinning assessment.
  • Extensions, second storeys and new homes: Planning Consent and Building Rules Consent. See extensions and renovations.
  • Granny flats: the Code's Deemed-to-Satisfy criteria for ancillary accommodation are a floor area up to 70 m², walls up to 3 m and a roof up to 5 m high; check the zone. Read granny flat rules in SA.
  • Pools deeper than 300 mm and their safety barriers. See pool engineering.
  • Retaining walls over 1 m, and wall-plus-fence combinations over 2.1 m. See retaining wall engineering.
  • Demolition of a local heritage place or a building in the Historic Area Overlay. Character Areas follow different rules, so check with council. Read looking after a bluestone home.
  • Excavation or fill over 9 m³ on coastal land (Schedule 3 clause 5).

What does a building consent application need?

Schedule 8 of the General Regulations lists what a Building Rules Consent application must include, and most of it comes from the designer and the engineer.

  • A site plan at 1:500, showing easements, trees that affect or are affected by the work, and "the location of any regulated tree on the site or on adjoining land"
  • Footing and structural drawings at 1:200, and specifications
  • "Calculations or reports", such as the engineer's structural calculations
  • "Details in writing of any foundation investigations": the site classification. See site classification and footings
  • Retaining walls: location, minimum and maximum heights, elevations at 1:200 and materials
  • Pools: a 1:200 plan with the pool's dimensions, safety features, setbacks from boundaries and pump location

What happens during and after the build?

The builder gives the council notice at set points, the council inspects, and the work finishes with a Statement of Compliance.

StepThe rule
Notices (reg 93)1 business day before work starts; before any stage the council specifies (1 business day in Metropolitan Adelaide, 2 outside it); any stage in the consent; 1 business day before completion. Penalty up to $10,000, expiation fee $750
Council inspectionsCurrent policies inspect 66% of new houses, 90% of new commercial buildings and 100% of new swimming pools
Statement of Compliance (reg 104)Part A signed by the licensed building work contractor (or, where there is none, a registered building work supervisor or a building certifier), Part B by the owner; lodged with any certificates or reports the consent lists. Not needed for Class 10 buildings other than pools and bushfire shelters
Occupancy (reg 103)A Class 10 building needs no certificate of occupancy. A house can't be lived in before completion unless it is structurally sound, weatherproof, has its facilities and smoke alarms, and meets the bushfire rules
Building indemnity insuranceThe builder needs it for domestic work costing $20,000 or more that needs approval, with $250,000 cover, and must give you the certificate before work starts. It is a builder's policy, not cover for engineering advice

PDI (General) Regulations 2017, PlanSA and SAFA. Owner-builders give the notices themselves.

When to call a structural engineer

Call an engineer as soon as you know the work touches the structure or the ground, so the drawings go in once and complete.

  • Your designer or certifier needs footing design, structural drawings or calculations
  • A Level 2 or Level 3 certifier needs the structural calculations independently certified. See engineer's certificates, from $390 + GST
  • A wall, deck or fence sits just over an exemption limit, or near a boundary
  • You plan to remove a wall and don't know whether it is load-bearing
  • The consent lists a certificate or report to lodge at completion

One fixed quote for the engineering

Send your plans or photos. We reply with a fixed quote in under 20 minutes on average, during business hours, and we say so if the job needs no engineer. Get a fixed quote.

Sources

  1. Planning, Development and Infrastructure (General) Regulations 2017 (SA), version of 29.10.2026. Schedule 4 clause 4 (work that is not development), reg 3C, reg 25, reg 57(8)(c), reg 93, reg 103, reg 104 and Schedule 8 clause 2(1)
  2. Planning and Design Code, Version 2026.19 (8 October 2026). The Code changes every fortnight; check the online Code for your site
  3. Department for Infrastructure and Transport, Fact sheet: Engaging an accredited professional as a decision-maker
  4. PlanSA, Inspections and compliance
  5. PlanSA, NCC 2025 state updates
  6. Legal Services Commission of SA, Law Handbook: retaining walls and fences
  7. SAFA, About building indemnity insurance
  8. sa.gov.au, Pool and spa safety

FAQ

Building approvals in SA: FAQs

Still unsure? Call 08 7083 9853 or send photos for a fixed quote.

What is the difference between Planning Consent and Building Rules Consent?

Planning Consent checks the proposal against the Planning and Design Code: the zone, overlays, siting and design. Building Rules Consent checks it against the Building Code: structure and the other technical rules. Together, with any other consent the work needs, they make Development Approval.

Who gives Building Rules Consent in SA?

The council, or an accredited professional building certifier. Building Level 1 covers any class of building, Level 2 buildings up to 3 storeys or 2,000 m², and Level 3 houses and outbuildings up to 2 storeys and 500 m². A Level 4 inspector can't grant consent.

Do I need approval for a retaining wall in SA?

Only if it retains more than 1 m of ground, or it is within 100 m of the coast, in a flood overlay or on a heritage place. A fence on top counts: over 2.1 m combined, from the low side, needs approval. Read retaining wall rules in SA.

Do I need approval to remove a load-bearing wall?

Yes. Internal alterations are exempt only when they remove nothing more than fixtures, fittings or non-load-bearing partitions and don't affect structural soundness, so a load-bearing wall needs consent and an engineer's beam design. See wall removal.

Does underpinning need approval in SA?

Usually it needs building consent. We confirm with your council or certifier for your job before any design starts, because the answer depends on the work and the building.

Is a deck exempt from approval in SA?

A deck is not development when no point is more than 500 mm above natural ground and no part is within 900 mm of a boundary. The exemption doesn't apply in a bushfire prone area, the Historic Area Overlay, the Coastal Areas Overlay, the Hills Face Zone or the Significant Landscape Protection Overlay.

Which NCC applies in South Australia?

NCC 2022 (as amended) is the Building Code until 30 April 2027. The NCC 2025 Building Code (Volumes 1 and 2) applies from 1 May 2027, and the NCC 2025 Plumbing Code has applied since 1 May 2026.

What does an engineer provide for a building consent application?

Structural drawings and calculations, a footing design to AS 2870 with the foundation investigation the application must describe, and independent certification of calculations where your certifier needs it. Certificates start from $390 + GST ($429 inc GST).