In short
Under section 139 of South Australia's PDI Act, a neighbour whose excavation cuts a 1V:2H plane starting 600 mm below ground at your boundary, or who fills within 600 mm of it, must serve a Form 1 notice at least 20 business days before work starts. You can then have a professional engineer specify shoring or underpinning, and they pay the reasonable cost.
Key takeaways
- The notice is a Form 1 Initial Notice to Owner of Affected Site, served at least 20 business days before work starts.
- Your engineer can specify shoring, underpinning or other strengthening. The person doing the work must follow it and pay the reasonable cost of the report and plans.
- Book a dilapidation report before the excavation starts. A dated record of existing cracks protects both sides.
- Work done without the required notice can bring a fine of up to $10,000.
An excavator next door, a basement going in or a boundary wall being cut can put your footings at risk. South Australia has a specific process for this in section 139 of the Planning, Development and Infrastructure Act 2016, and it gives you more control than most people expect, including your own engineer at the other side's cost.
Neighbour excavation: quick facts
- Excavation trigger
- Cuts a 1V:2H plane from 600 mm below ground at the boundary
- Fill trigger
- Fill within 600 mm of the boundary
- Notice
- Form 1, at least 20 business days before work
- Your engineer
- Specifies shoring or underpinning, at their cost
- Penalty
- Up to $10,000 for work without notice
- Dilapidation report
- From $690 + GST ($759 inc GST)
What is a section 139 notice?
A section 139 notice tells you that work proposed next door could affect the stability of your land, and starts your right to have it engineered safely. It is served on a "Form 1 Initial Notice to Owner of Affected Site" under regulation 64 and Schedule 10A of the PDI (General) Regulations 2017.
Two different "Form 1"s
The section 139 Form 1 is not the vendor's statement (also called a Form 1) that you receive when buying a house. If a neighbour's builder mentions a Form 1, it's the stability notice.
When does excavation or fill next door need a notice?
A notice is needed when an excavation cuts a notional plane sloping down at 1 vertical to 2 horizontal from a point 600 mm below natural ground level at the boundary, or when fill is placed within 600 mm of the boundary. Fill of 200 mm or less for landscaping is excluded.
Does the excavation trigger a section 139 notice?
| Distance of the dig from the boundary | Depth at which it cuts the plane |
|---|---|
| At the boundary | About 0.6 m |
| 1 m away | About 1.1 m |
| 2 m away | About 1.6 m |
| 4 m away | About 2.6 m |
Illustrative only, for level ground: 600 mm plus half the distance from the boundary. Sloping ground, existing walls and the actual excavation shape change the answer, so the engineer checks each case.
In practice that catches basements, swimming pools, deep footings, retaining wall cuts and service trenches close to the boundary, and fill built up against a boundary wall or fence.
How much notice must a neighbour give, and can they come onto my land?
The notice must be served at least 20 business days before the work starts, with enough detail for you to understand what is proposed. If the work needs access to your land, the notice says so, and the person doing the work must give at least one business day's notice before entering.
If you need more time, the Law Handbook suggests talking to the person proposing the work first. If that fails, you can apply to the Environment, Resources and Development Court to stop work starting. This is general information, not legal advice.
Can I get my own engineer, and who pays?
Yes. You can engage a professional engineer to report, with plans and specifications, on the need to shore up the excavation or to underpin, stabilise or otherwise strengthen your foundations. The person doing the work must comply with that advice and pay the reasonable costs of the report, plans and specifications.
- Who qualifies. Regulation 64 defines a professional engineer as a corporate member of Engineers Australia, or a person on the National Engineering Register, with civil or geotechnical competence.
- Costs. Payment of your engineer's reasonable costs can be enforced in the Environment, Resources and Development Court.
- Shared benefit. If you asked for the protection work, the builder may be able to recover part of its cost from you, by negotiation or court order.
South Australia does not currently register engineers, so the regulation's test (Engineers Australia membership or the National Engineering Register) is the one that counts here.
Which footings are at risk from an excavation?
Footings that sit within the excavation's zone of influence are the ones at risk. The deeper the dig and the closer it is to your footing, the more likely the ground under your house moves if the excavation isn't properly supported.
Is the neighbour's footing within the zone of influence?
The 45° line in Figure 2 is an engineering rule of thumb, not the legal trigger. The two are different tests: the section 139 plane (1V:2H from 600 mm below ground) decides whether a notice is needed, and the engineer's assessment decides what support the excavation and your footings need. Older houses with shallow footings, stone walls on lime mortar, and walls that already have cracks are the most sensitive. On reactive clay, a long-open excavation can also dry or wet the soil under your footings. See reactive clay soils.
Do I need a dilapidation report before my neighbour digs?
A dilapidation report isn't part of the section 139 process, but it is the most useful document you can have. It records the condition of your house before the work starts, so any new damage can be told apart from what was already there.
- Dated photos of every elevation and the rooms nearest the work
- Existing cracks mapped, measured and marked so they can be checked later
- Doors, windows, floors and paving that already stick, slope or have gaps
- Boundary walls, fences, retaining walls and paths near the excavation
- A follow-up survey after the works, compared with the first
Cracking blamed on neighbouring construction can end up a long way from a few patched cracks. In April 2026 a demolition application for a CBD heritage home built in 1851 went before the City of Adelaide's assessment panel after cracking allegedly caused by construction next door, with an engineering report saying the house was "not structurally safe to live in". Our dilapidation reports start from $690 + GST ($759 inc GST).

What should you do when you receive a section 139 notice?
- At least 20 business days out
Read the notice and the plans
Check the depth of the excavation or fill, its distance from the boundary and the start date.
- Before work starts
Book a dilapidation report
Have the condition of your house recorded, with dated photos and measured cracks.
- Before work starts
Engage a professional engineer
Your engineer reviews the proposed work and specifies shoring, underpinning or other strengthening where needed. The person doing the work pays the reasonable cost.
- Before work starts
Agree the protection works and access
The builder follows the engineer's advice and gives at least one business day's notice before entering your land.
- During and after
Monitor during and after the works
Check the marked cracks during the excavation and repeat the survey afterwards.
What if you're the one doing the excavation?
If you're the building owner, builder or designer, the same rules work in reverse: serve the Form 1 at least 20 business days before work starts, follow the neighbour's engineer's advice and pay their reasonable costs. Regulation 64 also says every building must be designed on the assumption that the neighbour may one day excavate to that 1V:2H plane.
A dilapidation report on the neighbour's house before you dig protects you from claims for damage that was already there. Excavating next to an existing retaining wall can also make you responsible for supporting it, and fill must not overload an existing wall. See retaining wall rules in SA and our page for builders and designers.
When should you call a structural engineer about neighbour excavation?
- You've received a section 139 notice and want the proposed work reviewed before it starts
- Excavation, demolition or piling is planned next door and you want a dilapidation report first
- New cracks have appeared since work started next door. See cracks in walls
- Your house is old stone, like many in North Adelaide and Norwood, or its footings are close to the boundary
- You're planning a basement, pool or deep footing near a boundary and need the notice and design right
What to send
The notice, any plans you were given and the start date. Get a fixed quote in under 20 minutes on average, during business hours, or call 08 7083 9853.
Need an engineer?
Received a section 139 notice?
Send the notice and any plans. You get a fixed quote for the engineering review or dilapidation report in under 20 minutes on average, during business hours.
Sources
- Legal Services Commission of South Australia, Law Handbook: Retaining walls. Notice to neighbours under section 139 of the PDI Act: triggers, Form 1, the professional engineer, costs and penalties
- Planning, Development and Infrastructure (General) Regulations 2017. Reg 64 (work affecting the stability of other land) and Schedule 10A (forms)
- Planning, Development and Infrastructure Act 2016 (SA), section 139
- InDaily, Too far gone: CBD heritage home faces the wrecking ball (9 April 2026)